Expansion of 3 new separate taxilanes E, G, J & F. AIP No. 3-49-0020-048-2025.
The project includes extensive phasing to allow for commercial and general aviation aircraft operations throughout the project, with zero required runway closures happening. The pavement geometry was altered to comply with current FAA design guidance, and miscellaneous project elements included safety area grading, stormwater grading and infrastructure, and subsurface drains. This project was complicated by the extremely weak subgrade conditions, which necessitated the use of geosynthetic stabilization fabric and additional subbase course thickness. The expansion of these 3 taxiplanes will allow for future growth for private, commercial, and public owners.